Hawthorne Road resurfacing was part of a larger 10-month Category 2 safety defects program.

AT A GLANCE

Initial Inspection (Nov 3, 2023)

Site visit with Kier, client, and contractor to assess 389m² for planing and resurfacing. After the site visit, client requested a larger area be covered (revised to 745m²).

Client Requirements

Birmingham City Council’s spend control officers required a depth of 100mm (AC20 DBM and SMA10 PMB 60psv). After local councilor’s intervention, there was a requirement for further expansion, the area increased to 1381m², focusing on the surface course.e course.

Safety Precautions

Traffic management precautions were taken to minimize disruption to the local area. Full road closure and pedestrian barriers installed on June 6, 2024, alongside a GPR survey.

Work Execution

Cold milling, hot-applied bond coat, installation of 60mm AC20 DBM, and 40mm SMA10 PMB completed over two days. Road markings were applied, and the road was reopened to public satisfaction.

For a more comprehsive overview of this project you can view our full case study for Hawthorne Road, simply click here.

SEE FOR YOURSELF

Words only go so far, we prefer to let our work speak for itself. Take a look at some of the pictures from our recent project on Hawthorne Road.

LATEST PROJECTS

20TH JULY 2024

SIGNALS UPGRADE / TM

BANTS LANE - NORTHAMPTON

12TH JUNE 2024

SURFACING

HAWTHORNE ROAD - BIRMINGHAM

10TH JUNE 2024

CIVILS

ABINGTON STREET - NORTHAMPTON

17TH JUNE 2023

ISO NHSS (NATIONAL HIGHWAYS SECTOR SCHEMES)

POPULAR PAGES